Skip to main content
Version: v2 beta

Hardware overview

This section describes the materials, components and equipment used in calculations. Equipment and use cases provide entry points; materials explain how composition or production processes affect the result.

Component modelling​

A component model makes configuration assumptions visible123:

Iequipment=Icpu+Iram+Istorage+Idisplay+Ibattery+IstructureI_{equipment}=I_{cpu}+I_{ram}+I_{storage}+I_{display}+I_{battery}+I_{structure}

This approach is parametric and modular, but does not automatically outperform a representative product LCA. Aggregate factors remain appropriate when their boundaries and evidence better match the assessment. See Equipment modelling.

From materials to services​

From components to services​

Old Open Data equipment and VM flat factors are obsolete for the target method. Illustrative magnitudes now come from explicit configurations evaluated with component models.

LevelRole in the calculation
ComponentCharacteristics and impact model with units, boundary and provenance
EquipmentComponent assembly plus a non-overlapping structural residual
Virtual resourceAllocated share of physical equipment and shared resources
ServiceSum of allocated contributions for the functional unit

The terminal and server examples follow this chain. Detailed calculations do not establish coefficient quality: exploratory assumptions remain identified in the register.

Embodied versus operational impacts

Manufacturing can dominate for low-power devices, depending on lifetime, usage and electricity mix. No universal percentage is assumed. Operational impacts can dominate for continuously running servers, particularly on higher-impact electricity. See Electricity impacts.

Section structure​

LayerChaptersPurpose
MaterialsSemiconductors; critical materialsProcesses, supply chains and origins of impacts
ComponentsCPU/GPU, RAM, storage, display, batteries, structuresParametric models and their evidence
EquipmentTerminals, servers, network equipmentAssembly, allocation and interactive scenarios
Network and infrastructureNetwork segments; datacentresShared-system modelling

Parametric models​

These models have different evidence levels. Node multipliers and display/battery factors include D4B assumptions; contextual publications do not validate those coefficients.

ObjectMain parametersGWP model / allocationEvidence
CPU dieDie area in mm², node scenario(die×0.0197+9.14)Fnode(die\times0.0197+9.14)F_{node}Historical UBA/Boavizta base; multiplier is a hypothesis
RAMGB capacity, physical density(capacity/density)×2.20+5.22(capacity/density)\times2.20+5.22 per moduleHistorical model; density and technology need justification
SSDGB capacity, NAND density(capacity/densityNAND)×2.20+6.34(capacity/density_{NAND})\times2.20+6.34 per driveHistorical model, not a universal modern-drive factor
HDDDrive count31.11 kg CO₂ eq. per driveHistorical fixed estimate
DisplayArea, technologyarea×Ctechnology+basearea\times C_{technology}+baseD4B scenario
BatteryWh capacity, chemistrycapacityWh/1000×Fchemistrycapacity_{Wh}/1000\times F_{chemistry}D4B scenario
NetworkTraffic and compatible distanceV×L×CFV\times L\times CF when the factor is per distanceHistorical system convention; reuse depends on current units and boundary

Indicator coverage​

IndicatorComponent-level evidenceRelevant processesCurrent status
GWPHistorical models and scenariosManufacturing and operational energyAvailable with explicit assumptions
ADPePartialHistorical CPU, RAM and SSD factorsLCIA compatibility required; battery not quantified
WUInsufficient for current component modelsProcess water and electricityPhysical and characterised water cannot be mixed; removed from CPU/RAM simulators
AP, PMAggregate inventories existManufacturing and useNo demonstrated component split
PEPartial historical modelsPrimary energyAdditional information, not electricity consumption
IRUnresolved historical unitLifecycle electricity and processesEquipment result withheld pending kg/kBq reconciliation
CTUe, CTUh-nc, CTUh-cAggregate data with variable qualityProcessing and extractionCompatible inventories and characterisation methods required
Actual coverage

The methodology's nine selected indicators are not all calculated by every simulator. Missing results are data gaps, not zero impacts. Primary energy is additional information outside that set. Editorial indicator groups are not endpoint damage models.

Assumptions and limitations​

  • Materials currently provide interpretation rather than an autonomous calculation model for every substance.
  • Component coefficients and D4B hypotheses require refinement as better inventories become available.
  • GWP and some historical ADPe factors are available; each chapter specifies their limits. Aggregated toxicity and particulate factors do not validate a component-level breakdown.
  • Networks remain heavily shared and are often represented through system factors.

Footnotes​

  1. Versioned equipment, cloud, country and electricity records in digital4better/data. Digital4Better data catalogue, snapshot 77cae4a. ↩

  2. Digital4Better, Green Cloud Computing, UBA, 2021; ADEME Base Empreinte; Tannu & Nair on SSD embodied carbon; Kelly et al. and Ellingsen et al. for battery context; Wang et al. and Kuo et al. for semiconductor environmental inventories; Digital4Better data (Digital4Better data.). Consult specialised chapters for source scope and factor validity.Evolving catalogue; pin a commit for reproducible factors. ↩

  3. Digital4Better, Digital4Better data.Evolving catalogue; pin a commit for reproducible factors. ↩